How pile optimization works
How pile optimization works
Maria Kuhareva avatar
Written by Maria Kuhareva
Updated over a week ago

After Cut&Fill is executed, pile optimization is performed.

Pile optimization has the following parameters:

  1. Max slope is the permissible slope of the tracker, in percent:

    height difference between the outermost piles of the tracker / tracker length * 100%
    ​

  2. Min pile reveal is the minimum required height from the surface to the crossbar with modules
    ​

  3. Max pile reveal - The difference in height between min reveal and max reveal is formed due to the tolerance of the ground surface during grading surface:

    max pile reveal = min pile reveal + 2 * tolerance
    ​

  4. Min pile embedment is the minimum height of a pile to which it must be driven into the ground to ensure a given load-bearing capacity

Example 1

Let's perform a Cut&Fill with tolerance = 0 ft and min pile reveal = 4 ft.

max pile reveal = min pile reveal + 2 * tolerance = 4 ft + 2 * 0 ft = 4 ft.

For 99% of trackers, this is what we get.

But since we always have an error in the Cut&Fill algorithm and the surface of the earth is discretized by a grid, we will always have a slight deviation for several trackers.

In this example, we got that one tracker exceeds the specified reveal by up to 0.3 ft.

Example 2

Let's perform a Cut&Fill with tolerance = 1 ft and min pile reveal = 4 ft.

max pile reveal = min pile reveal + 2 * tolerance = 4 ft + 2 * 1 ft = 6 ft.

From the sampling of the earth's surface by the grid and the error of the method, we have two trackers whose reveal exceeded the specified one by 1.8 ft.

But if Cut&Fill is restarted in areas where there is a large error for the reveal, setting greater accuracy for the algorithm, then we will get a result with a smaller error for the reveal.